7 issues in roads with high priority

HighRoads

County Line Road contractor delay

The ODOT contractor on the County Line Road widening walked off for five months; the city manager is sending letters to legislators and the governor and vowing tighter day counts on future ODOT contracts.

1 mentionLast discussed Sep 15, 2026
HighRoads

Aspen Avenue Phase 3 widening awarded

Cherokee Pride Construction wins the $4.78 million contract to widen Aspen Avenue from Jasper to Tucson — about $2 million under estimate — finishing the 2018 bond project after both intersections wrap up.

1 mentionLast discussed Aug 3, 2026
HighRoads

20th Street & Hillside Drive intersection fix

Traffic backs up to Kenosha at peak times near Adams Creek Town Center. Staff rejected a roundabout as too costly and picked a signal with added lanes, cutting backup from 500 feet to about 120 feet. Funded by the 2026 bond, with design starting now.

1 mentionLast discussed Jul 14, 2026
HighRoads

North Elder Place traffic and overnight semi-truck parking

Residents near the proposed Bricktown townhomes say North Elder Place is already congested, with semi-trucks parking overnight and construction traffic from the Structure Creek project. They want a traffic survey, no-parking signage, and code enforcement before 29 more households are added.

1 mentionLast discussed Jun 25, 2026
HighRoads

9th & Washington intersection bottleneck

Expect up to eight intermittent full closures at 9th (Lynn Lane) and Washington for intersection widening — one leg at a time, 9 a.m. to 4 p.m., with advance notice on signs and social media.

2 mentionsLast discussed Jun 15, 2026
HighRoads

RAISE Grant multimodal planning along Broken Arrow Expressway

The city has $5.84 million in federal planning money to redesign corridors around the Broken Arrow Expressway — sidewalks, trails, and traffic fixes on Kenosha, Elm and Lynn Lane. Some ideas, like closing business drives and limiting left turns, could be controversial, and the public gets its say Thursday night.

1 mentionLast discussed Apr 21, 2026
HighRoads

43rd Street railroad crossing agreement

After six years of work, the city is buying a Union Pacific crossing that connects 43rd Street to a signalized Highway 51 access — safer for the amphitheater, school and industrial park. The catch: a new $15,200 annual maintenance fee to the railroad that staff openly dislikes.

1 mentionLast discussed Apr 21, 2026