West Berm trail and parking lot improvements (change order)
Summary
A $4.2 million ordinance to fund the west bank levee berm project cleared first reading and heads to a final vote January 21.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Aug 26, 2026.
Impact analysis
$4.2 million proposed from fund balance — final vote pending.
West bank neighborhoods protected by flood control improvements.
Mentions & discussions (4)
Council Public Works Committee - Aug 26, 2026
A $60,950 change order adds trail rerouting and a brand-new parking lot at the soccer field on the west bank of the Arkansas River, wrapping up a $1 million ARPA grant for the area south of the refinery.
Council Public Works Committee - Jun 3, 2026
A $50,993.90 change order finishes the new concrete Rock Yard parking lot at Turkey Mountain, replacing gravel lots and adding pedestrian crossings.
Council Urban & Economic Development Committee - Jan 14, 2026
$5.2 million total repairs an eroded river berm near the West Bank soccer complex, fixing damage traced to the 2019 flood. The trail stays open with a reroute during construction.
Council (Regular) - Jan 14, 2026
A $4.2 million ordinance to fund the west bank levee berm project cleared first reading and heads to a final vote January 21.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tulsa
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.