Turkey Mountain parking improvements
Summary
A change order added $31,679.90 to stabilize slopes at the new west parking lot at Turkey Mountain, protecting the investment in trailhead parking.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Jun 3, 2026.
Impact analysis
$31,679.90 in added contract cost.
Trail users and visitors to Turkey Mountain.
Mentions & discussions (2)
Council Public Works Committee - Jun 3, 2026
A $50,993.90 change order finishes the new concrete Rock Yard parking lot at Turkey Mountain, replacing gravel lots and adding pedestrian crossings.
Council Urban & Economic Development Committee - Feb 25, 2026
A change order added $31,679.90 to stabilize slopes at the new west parking lot at Turkey Mountain, protecting the investment in trailhead parking.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Tulsa
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.