Stormwater project landscaping change order
Summary
A District 2 stormwater project (SW-23-01-01) is getting irrigation, plantings, fencing and landscaping added via a $182,812 change order — about 2.6% of the contract, well within the city's 10% limit — plus 21 extra days.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Aug 19, 2026.
Impact analysis
Adds $182,812.13 to the contract, about 2.57% of the original amount.
District 2 residents near the improved stormwater site.