Top issues during term (17)(Roads)
Gore Boulevard Traffic Signal Improvements
Full activation costs roughly $34,000-$35,000 per signal, covered by the $494,000 LMPO grant rather than city funds.
Neighborhood Traffic Control Measures
Modest sign and installation costs not itemized in the agenda.
Traffic calming on NW Oak and NW 35th
Standard traffic-calming installation cost, already vetted by the Streets & Development Committee.
Rogers Lane lighting improvements
$1,487,501.50 from capital project funds.
Citywide road safety study grant
$400,000 federal grant funds the study; implementation money could follow later.
ADA compliance and LATS bus conditions
Phase 4 Citywide Street Resurfacing
About $7.85 million from the 2019 Capital Improvement Fund.
Bridge improvement program
Bundling could lower construction costs, paid through ad valorem bond funds; no dollar figures were on the agenda.
SW Lee/SW 13th traffic signal retention
Avoids the cost of removing the signal but defers the efficiency savings staff identified.
South Lawton infrastructure and equity gap
CDBG funds could be directed toward street and drainage improvements in targeted neighborhoods.
LATS Transfer Center site purchase
$1.97 million from the Capital Improvement Program.
Goodyear Boulevard Phase 2 reconstruction
Property acquisition costs for the project; total reconstruction cost not stated at the meeting.
Citywide road rehabilitation
About $7.5 million combined across the three road rehabilitation contracts.
Sidewalk accessibility gaps
Streets and Development Committee established
Safe Streets federal planning grant
A $500,000 federal grant funds the safety study at no local cost.
Airport investment via FAA grants
Brings roughly $5.3 million in federal funding to airport projects.
Decisions during term (2)
Recorded while Hooton was in office — not necessarily decisions they moved, spoke to, or voted on.
Consider approving Change Order No. 2 in the amount of $102,310.45 and Final Pay App No. 20 in the amount of $448,948.94 for MTZ Construction, Inc. on Engineering project EN1707P2A - 2017 Ad Valorem Street and Roads Program (Residential)…
Consider approving Final Change Order No. 3 for MTZ Construction, Inc. on Engineering project EN1707P2B - 2017 Ad Valorem Street and Roads Program (Residential) Phase 2B, resulting in a reduction in the overall total contract of…
Voting record (0)(Roads)