Steeple Chase area storm sewer design overrun (Case 26-002)

Summary

A design contract came in $7,755 over what the committee and council authorized — caught during an audit. The committee recommended ratifying the extra spending to finish a 98-percent-complete design.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Feb 23, 2026.

Impact analysis

💰Financial impact

An extra $7,755 of 2018 bond funds on top of the original $35,000 authorization.

✅Who benefits

Residents along 195th East Avenue and East 37th Court South get a functioning storm sewer and city maintenance via easements.