Residential street rehabilitation awards
Summary
After more than a year of utility construction tearing up streets, the older Melinda Park neighborhood near 61st and Garnett is getting its roads repaved with a $2.66 million contract.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed May 19, 2026.
Impact analysis
$2,658,490 contract, less than the engineer's estimate.
Melinda Park residents, who have endured years of construction dust and damaged roads.
Short-term construction disruption and occasional complaints about site cleanliness, which staff said the contractor addresses quickly.
Mentions & discussions (3)
Broken Arrow City Council - May 19, 2026
Contracts for concrete panel replacement in South Park Estates and Steeple Chase subdivisions would repair worn residential streets.
Broken Arrow City Council - Apr 21, 2026
Remaining 2018 bond money is finishing out neighborhood street rehab, with Cherokee Pride winning two more contracts and staff crediting the contractor's bids with saving the city $3.5 million — enough to add three extra neighborhoods.
Broken Arrow City Council - Jan 20, 2026
After more than a year of utility construction tearing up streets, the older Melinda Park neighborhood near 61st and Garnett is getting its roads repaved with a $2.66 million contract.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Broken Arrow
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.