Adams Creek Reserve F weir reconstruction and East Seattle Court flooding (Case 26-003)
Summary
The weir structure behind the Dick's/Target center may not be detaining water as designed, sending peak flows into Westwind backyards near the high school. The committee recommended finishing plans and building the fix.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 23, 2026.
Impact analysis
Construction funds for the weir rebuild come from the 2018 bond; the exact total wasn't stated.
Downstream Westwind homeowners, especially the long-time resident who testified about flooding within 70–100 feet of her fence.
Mentions & discussions (1)
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Broken Arrow
What the council decided, in plain English — one email a week.